I haven’t been writing much for the last 7-8 months. I was
completely engrossed in construction of the house. It was hard work. I lost
more weight (I weigh 60 kg now) and feel much fitter. Mentally though, I am
drained. The house is yet not ready to move in. The rains have arrived. We did
our best to adequately cover the mud walls so as to protect them from rain and
moved to Mumbai. Hope that rains and thunderstorms will not cause any major
damage.
So much delay in getting the house ready was unexpected. After
almost 7 months, I haven’t been able to build a place suitable enough to stay. I’m
unable to describe how I feel about it. Just not able to find the words. It is
important that I articulate this feeling, more so for my own understanding, but
it is not happening right now. May be, I’ll try some other time.
The process of house construction was quite interesting. I
played the roles of an architect, a contractor, helper mason and manual
labourer. Of course, I was also the client too. The location of the house had
to be close to the water source. The first step therefore was to call the water
diviner to identify the spot, where I can bore a well. A hand pump appeared an
appropriate option for water as compared to an open well. Having identified the
spot, any further work could begin only after drilling the borewell, so that
we’re sure we’ve struck sufficient water. Drilling a borewell is a 3-4 hour
job, but finding the vendor was not quick.
In a rural setting, one should get that work done, for which
the vendor is available. The borewell vendor was not available immediately. The
next step was to create an elevation on which the house would be built. The
borewell spot having identified, I knew where the elevation could be created. Rocky
earth was to be dug and moved from nearby (approx 0.5 km away)to this location.
The JCB was available for a couple of days. In two days, 113 trolleys loads of
earth was moved creating an elevation of about 4.5’ in a 30’ X 40’ area. This
was based on a tentative layout of the house. Rekha was in staying Mumbai with
the kids then. We could not decide where we would stay till the house is ready
enough. The layout was still being discussed and the elevation was done. Not
the right sequence. Discussion about the layout was happening over phone.
Simulteneously I was trying to find someone, who will make the sun dried
bricks, the mason, manual labours and vendor for the borewell. There was a
phase, when nothing at all seemed to be moving. Days would pass without any
hint of progress. The experience of house building in Barkheda had taught me
that there is no point in forcing pace. Progress will happen only when the time
is ripe. So, I waited. Meanwhile, the layout plans kept getting modified. At
one stage, we felt that the elevation was created at the wrong place. But what
the heck; there was no option of relocating that much earth.
After one month, restlessness started creeping in. I was
staying away from my family in the hope that in about a month or 45 days, there
will be some place to start living – at least a small room. Now, this seemed
unlikely. Besides, city living was not doing the kids any good. We began
exploring options for living in some rented place. Nothing worthwhile was available in the
village. Devri, the nearest large village (7 km away) had options, but I was not
convinced about us staying in Devri and commuting to the farm to work on the
house construction. Rekha did not see any other option. Staying in Devri was,
from one perspective, better than staying in Mumbai.
Shashi had built a small mud house when he’d just shifted to
the land. This is a single room of approx 120 sq ft. During the last rains,
water had seeped through its floor. In October, it was impossible to live there.
The roof was also not water-proof. But we were in December. The room had
sufficiently dried. I felt that this option was not convenient, but better than
staying in Devri. Rekha was not convinced. The room had window and door frames
fitted, but no doors and windows. There was no toilet, no wash area or
bathroom, no water and electricity. I promised her that I’ll make it as livable
enough. We discussed the details and she agreed to consider, but only after
making one visit to inspect the place. For the door and windows, I got plywood
cut to the required size and fixed them in the frame with hinges. Doors and
windows done. One stone of 3’X2’ served as the washing area. One 100 litre tank
for water storage was our water source. Water was to be filled from Shashi’s
open well. If there is solar batteries are sufficiently charged, water can be
pumped, else carried in buckets for about 100 – 150 metres. We’d learnt to live
without electricity. We have a solar light (a very thoughtful gift from a
friend), which was good enough for the evening. Mobile and laptop could be
charged in Shashi’s house, also the occasional use of mixer or grinder. Toilet
was still a question mark. I did not need a toilet, because I used the fields.
The children could also be trained. Shashi had a conventional toilet in his
house, just in case we were not able to make any provision close by.
All this took almost a week, while efforts on other areas
were on. Rekha made a two day inspection visit. We had to choose the least out
of two or three inconvenient options. We chose to stay in the one room mud
house. Both of us made a Mumbai visit and returned with the kids.
The ordeal on the house construction front continued like a
thriller movie. There was no end in sight. The ‘to do’ list kept on increasing
but the ‘done’ list was almost blank. There were just too many vendors to be
found. Slowly, but surely, we found someone to make the sun-dried bricks, the
borewell vendor, the mason and labourers as well. After the borewell was done,
we had to recall the JCB for a day. 56 more trolleys of earth was moved to
create additional elevation around the proposed hand pump and additional width
to support the revised layout. My estimate of expense was quite ok, but
estimate of time turned out to be grossly wrong.
One factor, which posed unsurmountable challenge was
‘unseasonal rain’. It rained in every month since we shifted there. The ‘chaukas’ (sun-dried briks) were laid out
to dry in the sun. Approx 2000 chaukas
were made when the first bout of rain came in. The morning it became very
overcast, the labour were yet to come in. All 4 of us rushed to the work site
and began gathering the chaukas at
one place and stack them together. Each chauka
is nothing less than 5 kg. It was back-breaking task. It rained for about 2-3
days and we were happy we protected the chaukas.
After the rains, I realised that a few of them, which were exposed to rain, did
not wither away. Infact, they dried and were still fit to be used. Afterall, it
didn’t rain too much. When the rain
stopped and the sunlight was back, the chaukas
in stacks had to be again spread out to dry – another back breaking job.
Rain caused multiple damage. Firstly, there was no work on
the rainy day. Secondly, once the chaukas
were wet, they had to be given at least a week or 10 days of good sunlight to
dry. The amount of hardwork involved in stacking and un-stacking the chaukas led me to decide not to stack
them even when it rained. They could withstand minor showers for a couple of
days. So, the next bout of showers, I decided not to do anything. By this time,
5k were made, of which 2k were stacked. They chaukas braved another bout of rain. It caused delay because they
had to be left for drying again, but at least the effort to stack and unstack
was saved. Anyway I hadn’t found any regular labourers. Work continued in bits
and starts. Sometimes there was no work because people were unavailable,
sometimes rain.
But then it rained again, and again and once again. We’d
used up just about 1000 – 1500 chaukas out of 5000, when we realised that the
ones spread out have been quite badly damaged. Three bouts of rain proved to be
more than what they could bear. We were already in the beginning of March by
this time. Thoughts about the effort of re-doing and the amount of more time required
resulted in considerable depression.
Holi is a big festival in these areas. Our house was
supposed to be ready for occupancy by this time. But it was now clear that
we’ll have to restart much of the work. We took a break and visited a friend in
Kota.
Work began after we came back, but soon stopped, because it
was harvesting time. Labour was in demand and became scarce. Wages shot up. The
threat of rain was looming and even the farmers were concerned. I thought it
unfair and inappropriate that I should pay more as a reaction. I waited for
about a week. Harvesting was almost done but my boys were not to be seen. I
gave a re-thought to the wage issue. An increase in rate from 150 to 200 for
those working well seemed quite fair. I did so. From then on, there were a few
new boys on the scene. Work caught some pace and there was some respite from
rain.
The subsequent phase was quite also eventful. By early June,
pre-monsoon showers began. The mud house we were staying will become
unhabitable and the house is not fully ready. We were not able to find a vendor
to complete the roof work. The mud walls need to be protected from rain. We’ve
done a temperory roof and covered the walls with two layers of plastic sheets.
We’re back to Mumbai. It seems quite unlikely that we’ll be
able to finish any of the construction work during monsoon. Hope and pray that
there is no major damage to the work done so far. Rains apart, thunder storms
are an everyday affair in that area. Being in an open field, storms can cause
damage.